Question: The critical path in a project when resource constraints are considered as well as technological constraints when defining precedence constraints is known as the critical

The critical path in a project when resource constraints are considered as well as technological constraints when defining precedence constraints is known as the critical ______.

A. path methodology (CPM)

B. chain methodology (CCM)

C. point

D. mass

I answered (CPM), but was advised that this was wrong. I don't quite understand why as CPM deals with resource constraints and technological constraints, and this answer makes the most sense.