Question: The critical path on a project has 4 tasks, A , B , C , and D . The allowable amounts of crashing and the

The critical path on a project has 4 tasks, A, B, C, and D. The allowable amounts of crashing and the costs for crashing are given as
Task #days allowed $$$/day
A230
B350
C125
D215
To crash the project by 6 days,
A should be crashed by [ Select ]["0","2","3","1"] days.
B should be crashed by [ Select ]["1","3","2","0"] days.
C should be crashed by [ Select ]["0","2","3","1"] days.
D should be crashed by [ Select ]["2","1","3","0"] days.
The order of crashing these will be [ Select ]["BBBAAC", "ABBCDD", "DDCAAB", "DDCBAA"].
The total cost of crashing by 6 days will be[ Select ]["165","265","120","235"].

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!