Question: The critical path on a project has 4 tasks, A , B , C , and D . The allowable amounts of crashing and the
The critical path on a project has tasks, A B C and D The allowable amounts of crashing and the costs for crashing are given as
Task #days allowed $$$day
A
B
C
D
To crash the project by days,
A should be crashed by Select days.
B should be crashed by Select days.
C should be crashed by Select days.
D should be crashed by Select days.
The order of crashing these will be Select BBBAAC "ABBCDD", "DDCAAB", "DDCBAA"
The total cost of crashing by days will be Select