Question: The critical path on a project has 4 tasks, A , B , C , and D . The allowable amounts of crashing and the

The critical path on a project has 4 tasks, A, B, C, and D. The allowable amounts of crashing and the costs for crashing are given as
\table[[Task,Adays allowed,$$$ day,\table[[I of days],[Crashed]],Cost],[A,2,30,,],[B,3,50,,],[C,1,25,,],[D,2,15,,]]
DRAW:
To crash the project by 6 days,
A should be crashed by [blank1] days.
B should be crashed by [blank2] days.
Cshould be crashed by [blank3] days.
D should be crashed by [blank4] days.
The order of crashing these will be [blank5].
The total cost of crashing by 6 days will be[blank6].
 The critical path on a project has 4 tasks, A, B,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!