Question: The critical path on a project has 4 tasks, A , B , C , and D . The allowable amounts of crashing and the

The critical path on a project has 4 tasks, A, B, C, and D. The allowable amounts of crashing and the costs for crashing are given as
\table[[Task,#daysallowed,$$$? day,\table[[# of days],[Crashed]],Cost],[A,2,30,15,15],[B,3,50,16.6666667,33.33333],[C,1,25,25,0],[D,2,15,7.5,7.5],[,,,,$55.83