Question: The criticat path for the network activities shown below is with duration table [ [ , , Immediate ] , [ Activity , Duration,Predecessors

The criticat path for the network activities shown below is with duration
\table[[,,Immediate],[Activity,Duration,Predecessors],[A,10,---],[B,8,--],[C,5,A],[D,4,A],[E,5,B,C,D]]
A. A-C-E; 18
B. A-C-E; 20
C. B-E; 13
D. A-D-E; 19
E. A-B-C-D-E; 29
 The criticat path for the network activities shown below is with

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!