Question: The data provided in the table below are provided for the Master Production Schedule of one of Company X's products. Based on this information what

The data provided in the table below are provided
The data provided in the table below are provided for the Master Production Schedule of one of Company X's products. Based on this information what is the projected on-hand inventory in period two? Beginning Inventory = 43; MPS quantity = 80 Week 1 Week 2 Week 3 Forecast 20 Orders Projected On-Hand Master Production Schedule Available-to-Promise o 21 O 12 04 43