Question: The early activity start is determined by Select one: a . The lag of an activity. b . The free float of an activity. c
The early activity start is determined by
Select one:
a The lag of an activity.
b The free float of an activity.
c The latest of the early finish times of all immediate preceding activities.
d The earliest time all immediate preceding activities can finish.