Question: The late activity start is determined by Select one or more: a . The early activity start and free float. b . The late activity
The late activity start is determined by
Select one or more:
a The early activity start and free float.
b The late activity finish time only.
c The late activity finish time and duration.
d The early activity start time and total float.