Question: The earned value on your project is $150,000, the planned value is $200,000. You've actually spent $180,000 to date. What is the efficiency rate of
The earned value on your project is $150,000, the planned value is $200,000. You've actually spent $180,000 to date. What is the efficiency rate of your schedule or the SPI of your project