Question: The earned value on your project is $150,000, the planned value is $200,000. You've actually spent $180,000 to date. What is the efficiency rate of
The earned value on your project is $150,000, the planned value is $200,000. You've actually spent $180,000 to date. What is the efficiency rate of your schedule or the SPI of your project? $45,000 0
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
