Question: The estimates for task H (in weeks) 5, 7, and 12, respectively, were for optimistic, most likely, and pessimistic times used in planning a project.
The estimates for task H (in weeks) 5, 7, and 12, respectively, were for optimistic, most likely, and pessimistic times used in planning a project. What is the variance for this task?
(Round your answer to two decimal places, if it has any decimals.)