Question: The estimates for task G (in weeks) 3, 8, and 13, respectively, were for optimistic, most likely, and pessimistic times used in planning a project.
The estimates for task G (in weeks) 3, 8, and 13, respectively, were for optimistic, most likely, and pessimistic times used in planning a project. What is the variance for this task? (Round your answer to two decimal places, if it has any decimals.)