Question: The expected activity time in PERT analysis is calculated as: Part 2 A . the simple average of the optimistic, pessimistic, and most likely times.
The expected activity time in PERT analysis is calculated as:
Part
A
the simple average of the optimistic, pessimistic, and most likely times.
B
the sum of the optimistic, pessimistic, and most likely times.
C
the sum of the optimistic, pessimistic, and most likely times, divided by six.
D
the sum of the activity variances, divided by six.
E
the weighted average of a m and b with m weighted times as heavily as a and b