Question: The expected activity time in PERT analysis is calculated as a. the simple average of the optimistic, pessimistic, and most likely times b. the weighted

 The expected activity time in PERT analysis is calculated as a.

The expected activity time in PERT analysis is calculated as a. the simple average of the optimistic, pessimistic, and most likely times b. the weighted average of a, m, and b, with a weighted 4 times as heavily as a and m the sum of the activity variances, divided by six O d. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b O e. the weighted average of a, m, and b, with b weighted 4 times as heavily as m and b

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!