Question: The expected activity time in PERT analysis is calculated as: Select one: A . the simple average of the optimistic, pessimistic, and most likely times.
The expected activity time in PERT analysis is calculated as:
Select one:
A the simple average of the optimistic, pessimistic, and most likely times.
B the sum of the optimistic, pessimistic, and most likely times.
C the sum of the optimistic, pessimistic, and most likely times, divided by six.
D the weighted average of and with weighted times as heavily as a and
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
