Question: The expected time for a project is 20 months with a variance of 4. What is the probability the project will take more than 23

The expected time for a project is 20 months with

The expected time for a project is 20 months with a variance of 4. What is the probability the project will take more than 23 months? Select one: O a. None of the other options O b. 0.77337 O c. 0.06681 O d. 0.93319 O e. 0.22663 Check

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!