Question: the following assumptions, develop a cost estimate that integrates all of the cost elements to the customer. What is the total cost for the project?
the following assumptions, develop a cost estimate that integrates all of the cost elements to the customer. What is the total cost for the project? How long will this project take to 17 (5 points) Given a final bid price to th complete? Sunction points in the project: 278 Software engineers assigned to this team: 4 action point productivity per software engineer: 5 per month Workdays per typical month: 22 Productive hours per typical workday: 8 hourly wage rate per software engineer (does not include fringe benefits): S50 per hour Overhead (fringe benefit, other direct overhead) rate: 32% G&A rate: 11.5% Proposed profit: 10%