Question: The following data was obtained from a WAN project: Activity Duration Predecessors A 3 Days --- B 6 Days --- C 3 Days A D
The following data was obtained from a WAN project:
| Activity | Duration | Predecessors |
| A | 3 Days | --- |
| B | 6 Days | --- |
| C | 3 Days | A |
| D | 2 Days | B |
| E | 3 Days | B |
| F | 1 Day | C, D |
| G | 5 Days | C, D |
| H | 4 Days | E, F, G |
| I | 7 Days | E, F |
- Construct a network diagram for the project. MS Excel, Word, or MS Project (1 pt)
- Calculate the scheduled completion time and identify the critical path. (2 pts)
- What is the slack time (float) for activities A, D, E, and F?