Question: The following information about a project is given below: table [ [ Activity , table [ [ Predecessor ] , [ Activity ]

The following information about a project is given below:
\table[[Activity,\table[[Predecessor],[Activity]],Duration (Weeks)],[A,,2],[B,,2],[C,,4],[D,A,B,4],[E,B,4],[F,B,2],[G,F,C,6],[H,B,3],[I,E,H,2],[J,E,H,2],[L,C,D,F,J,2],[L,K,4]]
a. Draw the network for the above project.
b. Determine the critical path and total duration of the project.
 The following information about a project is given below: \table[[Activity,\table[[Predecessor],[Activity]],Duration (Weeks)],[A,,2],[B,,2],[C,,4],[D,A,B,4],[E,B,4],[F,B,2],[G,F,C,6],[H,B,3],[I,E,H,2],[J,E,H,2],[L,C,D,F,J,2],[L,K,4]]