Question: The following list represents a project. Activity Normal time Crash time Crash cost (day) (days) Predecessor per day A 8 6 $460 B 1 $260

The following list represents a project. Activity
The following list represents a project. Activity Normal time Crash time Crash cost (day) (days) Predecessor per day A 8 6 $460 B 1 $260 2 $60 A D 2 $1ho AB E 1 $400 C D To cut one day from the project's duration, how much (in dollars) is added to project cost? NaaN 00 Your