Question: please help me on this one Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B
please help me on this one
Consider the following: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 2200 2600 B 2 1 2400 2800 3 3 500 500 D 8 4 2200 2600 E 6 3 600 1200 B. F 3 2 3600 4200 G 4 2 1200 2000 DE What is the cost for crashing the project by 4 days? Your