Question: The following list represents a project. Activity Normal time Crash time Crash cost (day) (days) Predecessor per day A 8 6 $460 B 2 1

The following list represents a project. Activity
The following list represents a project. Activity Normal time Crash time Crash cost (day) (days) Predecessor per day A 8 6 $460 B 2 1 $260 C 7 2 $85 A 7 2 $90 , E 2 1 $400 C D To cut one day from the project's duration, how much (in dollars) is added to project cost