Question: Consider a project: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 200 260 B 2 1 220 280 3 3

Consider a project: Activity Normal time Crash

Consider a project: Activity Normal time Crash time Normal cost Crash cost Predecessor A 4 3 200 260 B 2 1 220 280 3 3 3 3 50 50 8 4 230 260 A 6 3 90 570 B F 3 2 2 300 420 G 4 2 140 200 DE What is the crash cost per time-unit for activity E? WOOOWN Your