Question: The following project construct a Grant chart. Activity Predecessor(s) Duration (days) Activity Predecessor(s) Duration (days) A 1 E B 3 B A 3 F C,D
The following project construct a Grant chart.
Activity Predecessor(s) Duration (days) Activity Predecessor(s) Duration (days) A 1 E B 3 B A 3 F C,D 1 C A 2 G F 2 D A 4 H E,G 4
Using the project in problem 1, construct the project network and list all of the possible pathways to completion. Determine the critical path(s). What are the critical path days to completion?