Question: The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C D EFGH F A A B C, D

The following represents a project that should be scheduled using CPM: b. What is the critical path? A-D.G.H A-D.F.H B.E.G.H A.C.F.H c. What is thijexpected project completion time? (Do not round intermediate calculations, Round your answer to 3 decimal places.)