Question: The following represents a project that should be scheduled using CPM: b. What is the critical path? A-C-F-H A-D-F-H A-D-G-H B-E-G-H c. What is the
The following represents a project that should be scheduled using CPM:

b. What is the critical path?
-
A-C-F-H
-
A-D-F-H
-
A-D-G-H
-
B-E-G-H
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
IMMEDIATE ACTIVITY PREDECESSORS A B C A D A E B F G D, E H F,G TIMES (DAYS) a b 1 4 7 1 3 5 2 5 11 1 8 9 1 2 3 1 6 11 1 2 2 3 ww woon C,D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts