Question: The following table lists the tasks, the expected activity times, and preceding tasks for a project. TASK Preceding Task Task Length A None 5 B
The following table lists the tasks, the expected activity times, and preceding tasks for a project.
| TASK | Preceding Task | Task Length |
| A | None | 5 |
| B | None | 3 |
| C | A | 2 |
| D | B | 5 |
| E | C | 1 |
| F | D | 3 |
| G | E,F | 4 |
1. Draw the project network diagram. Be sure to include the START and END nodes and arrows between activities.
2. List the activities on the Critical Path?
3. Which activities have slack and how much?
4. In order to speed up the project, Koby recommends paying overtime to reduce the time for activity D. Lilly recommends hiring temp staff to speed up activity E. Do you agree with Koby or Lilly? Why or why not??
Use a full size clean white 8.5x11 sheet of paper and hand draw a NEAT and ORGANIZED project network diagram. Neatly add ES, EF, LS, and LF to each node. I recommend using multiple colored pens/pencils. Neatly ANSWER questions 2, 3, and 4 on the same paper below the diagram. Either scan or take a picture of your page and upload it for this question.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
