Question: The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. Task Preceding Tasks A None B

The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project.
Task……………… Preceding Tasks
A……………… None
B……………… None
C……………… A
D……………… B
E……………… C, D
F……………… E
G……………… F