Question: The following table lists the tasks, the expected activity times, and preceding tasks for a project. 1. Draw the project network diagram. Be sure to

The following table lists the tasks, the expected activity times, and preceding tasks for a project. 1. Draw the project network diagram. Be sure to include the START and END nodes and arrows between activities. 2. List the activities on the Critical Path? 3. Which activities have slack and how much? 4. In order to speed up the project, CHA recommends paying overtime to reduce the time for activity B. WANG recommends hiring temp staff to speed up activity D. Do you agree with CHAN OR WANG? Why or why not? The following table lists the tasks, the expected activity times, and preceding tasks for a project. 1. Draw the project network diagram. Be sure to include the START and END nodes and arrows between activities. 2. List the activities on the Critical Path? 3. Which activities have slack and how much? 4. In order to speed up the project, CHA recommends paying overtime to reduce the time for activity B. WANG recommends hiring temp staff to speed up activity D. Do you agree with CHAN OR WANG? Why or why not
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts