Question: write neat for thumbs up The following table lists the tasks, the expected activity times, and preceding tasks for a project. TASK Preceding Task Task
write neat for thumbs up
The following table lists the tasks, the expected activity times, and preceding tasks for a project. TASK Preceding Task Task Length A None 5 A B A 3 00 B N 2 D 6 None AD E 1 F N 2 G F 2 1. Draw the project network diagram. Be sure to include the START and END nodes and arrows between activities. 2. List the activities on the Critical Path? 3. Which activities have slack and how much? 4. In order to speed up the project, Abby recommends paying overtime to reduce the time for activity B. Michael recommends hiring staff to speed up activity D. Do you agree with Abby or Michael? Why or why not? S 2 7 O . 00 s PAS