Question: The following table represent a software development project study the table and answer the questions? Activity Immediate Duration predecessor Weeks A 2 B 3 A

The following table represent a software
The following table represent a software development project study the table and answer the questions? Activity Immediate Duration predecessor Weeks A 2 B 3 A 5 D A,B E CD 4 F D 12 G E 2 H G 1 6 a) Draw Network Diagram representing the project? List the paths of the project? b) What is the critical path and what is the duration? c) Calculate the slack for each activity? d) By how many weeks we can delay activity E without affecting the project duration