Question: The following table represents a plan for a project: PREDECESSOR JOB(S)TIMES (DAYS)JOB NO. amb 1-138211293114741126522466335774361285,623498147107345119,10567 b. Indicate the critical path. 1-3-6-8-9-111-2-5-81-2-5-8-9-111-4-7-10-11 c. What is the

The following table represents a plan for a project:

PREDECESSOR

JOB(S)TIMES (DAYS)JOB NO.amb1-138211293114741126522466335774361285,623498147107345119,10567

b.Indicate the critical path.

1-3-6-8-9-111-2-5-81-2-5-8-9-111-4-7-10-11

c.What is the expected completion time for the project?(Round your answer to 2 decimal places.)

Expected completion timedays

d.You can accomplish any one of the following at an additional cost of $2,000 and if you will save $1,500 for each day that the earliest completion time is reduced, which action, if any, would you choose?

1.Reduce job 5 by two days.

YesNo

2.Reduce job 3 by three days.

YesNo

3.Reduce job 6 by two days.

YesNo

e.What is the probability that the project will take more than 29 days to complete?(Round your answer to 2 decimal places.)

Probability

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!