Question: The following table represents a plan for a project: PREDECESSOR JOB(S)TIMES (DAYS)JOB NO. amb 1-138211293114741126522466335774361285,623498147107345119,10567 b. Indicate the critical path. 1-3-6-8-9-111-2-5-81-2-5-8-9-111-4-7-10-11 c. What is the
The following table represents a plan for a project:
PREDECESSOR
JOB(S)TIMES (DAYS)JOB NO.amb1-138211293114741126522466335774361285,623498147107345119,10567
b.Indicate the critical path.
1-3-6-8-9-111-2-5-81-2-5-8-9-111-4-7-10-11
c.What is the expected completion time for the project?(Round your answer to 2 decimal places.)
Expected completion timedays
d.You can accomplish any one of the following at an additional cost of $2,000 and if you will save $1,500 for each day that the earliest completion time is reduced, which action, if any, would you choose?
1.Reduce job 5 by two days.
YesNo
2.Reduce job 3 by three days.
YesNo
3.Reduce job 6 by two days.
YesNo
e.What is the probability that the project will take more than 29 days to complete?(Round your answer to 2 decimal places.)
Probability