Question: The following table represents a plan for a project: Use Appendix G. TIMES (DAYS) PREDECESSOR JOB NO. JOB(S) 1 2 1 3 1 4 1

The following table represents a plan for a

The following table represents a plan for a project: Use Appendix G. TIMES (DAYS) PREDECESSOR JOB NO. JOB(S) 1 2 1 3 1 4 1 5 2 6 3 7 4 8 5,6 9 8 10 7 11 9, 10 1 1 2 2 3 2 1 1 W pour voiONO A3 b 9 12 9 9 8 11 12 10 8 7 14 b. Indicate the critical path. O 1-4-7-10-11 O 1-2-5-8-9-11 O 1-2-5-8 1-3-6-8-9-11 c. What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Expected completion time days