The following table represents a plan for a project:
TIMES DAYS
JOB NO PREDECESSOR
JOBS a m b
b Indicate the critical path. multiple choice
c What is the expected completion time for the project? Do not round intermediate calculations. Round your answer to decimal places.
d You can accomplish any one of the following at an additional cost of $ If you will save $ for each day that the earliest completion time is reduced, which of the following actions should be taken, if any?