Question: The following table represents a plan for a project: Use Appendix G. TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 3 5 10
The following table represents a plan for a project: Use Appendix G.
| TIMES (DAYS) | ||||
| JOB NO. | PREDECESSOR JOB(S) | a | m | b |
| 1 | 3 | 5 | 10 | |
| 2 | 1 | 2 | 2 | 14 |
| 3 | 1 | 2 | 5 | 8 |
| 4 | 1 | 1 | 4 | 10 |
| 5 | 2 | 1 | 3 | 5 |
| 6 | 3 | 2 | 4 | 6 |
| 7 | 4 | 3 | 6 | 12 |
| 8 | 5, 6 | 1 | 4 | 7 |
| 9 | 8 | 2 | 6 | 13 |
| 10 | 7 | 3 | 4 | 5 |
| 11 | 9, 10 | 1 | 7 | 13 |
Indicate the critical path
a) 1-3-6-8-9-11
b) 1-4-7-10-11
c) 1-2-5-8
d) 1-2-5-8-9-11
| What is the expected completion time for the project? in days |
| You can accomplish any one of the following at an additional cost of $1,500. If you will save $1,000 for each day that the earliest completion time is reduced, which of the following actions should be taken, if any? 1. Reduce job seven by 2 days? yes or no 2) reduce job three by 3 days? yes or no 3) reduce job eight by 4 days? yes or no What is the probability that the project will take more than 35 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) |