Question: The following table represents a plan for a project: Use Appendix G. TIMES (DAYS) JOB NO. PREDECESSOR JOB(S) a m b 1 3 5 10

The following table represents a plan for a project: Use Appendix G.

TIMES (DAYS)

JOB NO. PREDECESSOR JOB(S) a m b
1 3 5 10
2 1 2 2 14
3 1 2 5 8
4 1 1 4 10
5 2 1 3 5
6 3 2 4 6
7 4 3 6 12
8 5, 6 1 4 7
9 8 2 6 13
10 7 3 4 5
11 9, 10 1 7 13

What is the expected completion time for the project? (Do not round intermediate calculations. Round your answer to 2 decimal places.)

What is the probability that the project will take more than 35 days to complete? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!