Question: The following table shows the current status data for a project at the end of month 3. PV (Planned Value) EV (Earned Value) AC (
The following table shows the current status data for a project at the end of month 3.
| PV (Planned Value) | EV (Earned Value)
| AC (Actual Cost)
| SV | CV | SPI | CPI |
| $18,461.54 | $35,673.08 | $20,673.08 |
|
|
|
|
If you were the project manager for this project, should you have any concerns about this data?
If yes, then
- what are your concerns?
- what might be some underlying causes?
- how might you combat these in the future?
If no, then explain why not.