Question: The following table shows the time estimates for the setup of a new production line at Ithaca Custom Manufacturing (ICM) Inc. The time is measured

The following table shows the time estimates for the setup of a new production line at Ithaca Custom Manufacturing (ICM) Inc. The time is measured by weeks.

Activity

Time

Predecessor and Lag

A

4

-

B

2

A (FS+2)

C

3

A

D

3

B, C

E

4

B, C

F

2

D, E

  1. Develop an Activity-On-Node (AON) network diagram and calculate the project completion time.
  2. Identify the critical path.
  3. Calculate the Free Slack and Total Slack for each of the non-critical activity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!