Question: The following table shows the time estimates for the setup of a new production line at Ithaca Custom Manufacturing (ICM) Inc. The time is measured
The following table shows the time estimates for the setup of a new production line at Ithaca Custom Manufacturing (ICM) Inc. The time is measured by weeks.
| Activity | Time | Predecessor and Lag |
| A | 4 | - |
| B | 2 | A (FS+2) |
| C | 3 | A |
| D | 3 | B, C |
| E | 4 | B, C |
| F | 2 | D, E |
- Develop an Activity-On-Node (AON) network diagram and calculate the project completion time.
- Identify the critical path.
- Calculate the Free Slack and Total Slack for each of the non-critical activity.