Question: The information about a project with 10 activities is shown below. Activity A; 10 days; IP = none Activity B; 19 days; IP = none

The information about a project with 10
The information about a project with 10
The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 10 days; IP = none Activity B; 19 days; IP = none Activity C; 24 days; IP = A Activity D; 33 days; IP = A, B Activity E; 38 days; IP = B Activity F: 22 days; IP = C, D Activity G; 13 days; IP = C, D Activity H; 27 days; IP = E Activity K; 9 days; IP = F Activity M: 26 days; IP = G, H The latest start time of activity D is at the end of day