Question: The information about a project with 10 activities is shown below. Activity A; 23 days; IP = none Activity B; 18 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 23 days; IP = none Activity B; 18 days; IP = none Activity C; 39 days; IP = A Activity D: 31 days; IP = A, B Activity E; 29 days; IP = B Activity F: 39 days; IP = C, D Activity G; 14 days; IP = C, D Activity H: 45 days: IP = E Activity K, 21 days; IP = F Activity M: 11 days: IP = G. H The earliest finish time of activity Mis at the end of day