Question: The information about a project with 10 activities is shown below. Activity A; 17 days; IP = none Activity B: 22 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 17 days; IP = none Activity B: 22 days; IP = none Activity C; 44 days; IP = A Activity D; 22 days; IP = A, B Activity E; 43 days; IP = B Activity F; 21 days, IP = C, D Activity G: 20 days; IP = C, D Activity H; 32 days; IP = E Activity K; 6 days; IP = F Activity M; 14 days; IP - GH The earliest finish time of activity M is at the end of day