Question: The information about a project with 10 activities is shown below. Activity A; 17 days; IP = none Activity B: 19 days; IP = none

The information about a project with 10
The information about a project with 10 activities is shown below. Activity A; 17 days; IP = none Activity B: 19 days; IP = none Activity C; 12 days; IP = A Activity D: 25 days; IP = A,B Activity E; 23 days; IP = B Activity F; 33 days: IP-C Activity G; 16 days; IP D Activity H: 22 days: IP = E Activity K; 22 days; IP-FG Activity M: 7 days; IP-G, H The earliest start time of activity K is at the end of day