Question: The latest start time for an activity is equal to the latest finish time minus the activity time. True False Question 4 1 pts Activities
The latest start time for an activity is equal to the latest finish time minus the activity time.
True
False
Question
pts
Activities on the critical path have a slack time equal to zero.
True
False