Question: QUESTION 5 Given is a CPM project network diagram as shown below. C F Start E . End B D G A B D E

QUESTION 5 Given is a CPM project network diagram

QUESTION 5 Given is a CPM project network diagram as shown below. C F Start E . End B D G A B D E F G H Activity day Start 0 8 End 0 6 3 7 4 9 4 6 a) The Project Cor etion time = days b) The Earliest Start time, ES, of Activity G- days. c) The Latest Finish time, LF, of Acitivity - days. d) The critical activities are = (ex. Fill in answer as: ABCD) QUESTION 6 Ane comnany that reduces pleasure boats has decided to expand one of its lines. The company is considering three Location