Question: The likelihood the original critical path ( s ) will change once the project is initiated is referred to as Group of answer choices Rigidity.
The likelihood the original critical paths will change once the project is initiated is referred to as
Group of answer choices
Rigidity.
Flexibility.
Sensitivity.
Resilience.
Concurrent engineering.