Question: The likelihood the original critical path ( s ) will change once the project is initiated is referred to as Rigidity. Flexibility. Resilience. Concurrent engineering.

The likelihood the original critical path(s) will change once the project is initiated is referred to as
Rigidity.
Flexibility.
Resilience.
Concurrent engineering.
Sensitivity.
 The likelihood the original critical path(s) will change once the project