Question: The Master Production Schedule ( MPS ) : Question 3 5 options: A . A listing of all raw materials, sub - assemblies and parts

The Master Production Schedule (MPS):
Question 35 options:
A. A listing of all raw materials, sub-assemblies and parts needed to produce one unit of production
B. Is a time-phased plan specifying timing and quantity of production for each end item
C. Determines the plans for purchasing and production of independent demand concepts
D. Output of sub-assemblies or component parts used in the production of finished goods
E. Uses extensive software to integrate record keeping and information sharing throughout the organization