Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5 , B = 2 , C
The network below represents a project being analyzed by the critical path method. Activity durations are and
a What task must be on the critical path, regardless of activity durations?
b What is the duration of path
c What is the critical path of this network?
d What is the length of the critical path?
e What is slack time at activity
What is the Late Finish of activity
g If activity were delayed by two time units, what would happen to the project duration?