Question: The network below represents a project being analyzed by the critical path method. Activity durations are A = 5 , B = 2 , C

The network below represents a project being analyzed by the critical path method.
Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=
10, and J=6.(Marks 10)
a. What tasks must be on the critical path?
b. What is the duration of path A-B-E-H-J?
c. What is/are the critical path(s) of this network?